CATALAYER NEWS

The brutal $346M math behind Galaxy’s high-stakes race to build CoreWeave’s Texas AI mega-center

Source: CryptoSlate · 2026-07-26
Galaxy Digital’s $3.507 billion financing for its CoreWeave data-center build in Texas comes with a steep price: about $346.3 million in annual interest. A Galaxy project subsidiary priced the 9.875% senior secured notes on July 23. The deal is slated to close July 28, and the notes mature on Aug. 1, 2031 . The financing is intended to cover part of two buildings with eight data halls at the Helios campus. The facilities are planned for 400 megawatts of utility capacity and 260 MW of critical IT
RELATED ON CATALAYER
Mentioned Tickers
$CRWV · CoreWeave
Related Topics
AI Stocks News & Analysis
RELATED MARKETS
Prediction Markets
New Rihanna Album before GTA VI?50%New Playboi Carti Album before GTA VI?50%Will Jesus Christ return before GTA VI?50%
Open Catalayer terminal for live tracking →